Project Location: | Louisville, Kentucky |
| Contact: | See Below
502-540-6000
|
Company: | LOUISVILLE & JEFFERSON COUNTY MSD |
| PreBid Date: |
3/12/2010 1:30 P.M.
|
Bid Opening Date: |
4/7/2010 12:00 P.M.
|
| PreBid Information: | Non-Mandatory Meeting -- Location: Intersection of S. 4th Street and W. Oak Street
|
| Bid Information: | Location: MSD Main Office Conference Room 1080 @ 700 W. Liberty St., Louisville, KY 40203
|
| Specs: |
Download Full RFP
|
Public Notes: |
Bid Results
Sealed Bids are invited for the construction of:
Project Name: 4th Street Sewer Replacement Project Contract No. 2009-131 Budget I.D. No. B10144
This Contract involves installation of replacement pipe for the 24" brick sewer along the 1100 Block of S. 4th Street between W. Oak Street and W. St. Catherine Street. The major items of construction include, but are not limited to, the following:
1. Remove and replace approx. 800 L.F. 24-Inch Sanitary Sewer. 2. Handle existing flows during construction. 3. Replace 5 Manholes. 4. Install saddles to reconnect all property service connections. 5. Resurface approximately 2,440 S.Y. roadway. 6. All associated work. All work will be done in accordance to MSD’s Standard Specifications.
The engineer's estimate for this project is greater than $50,000; therefore, in accordance with MSD's Supplier Diversity (MBE/WBE Participation) Contractor Compliance Program (CCP), Supplier Diversity goals shall be required for this project. The Supplier Diversity goals are 15% MBE and 6% WBE participation. MBE/WBE contractors must be certified prior to the bid opening (Click here to access the certified list).
Supplier Diversity required forms including the MBE/WBE Data Sheet, Proposal and Bid Certificate should be submitted for each MBE/WBE subcontractor. For a copy of MSD’s Contractor Compliance Program and Supplier Diversity required forms and instructions go to MSD’s Suppliers Diversity Website.
MSD gives preference to local businesses seeking to do business as suppliers or prime contractors which are defined as businesses that have headquarters or a branch office currently located in Louisville Metro that has been located in this area for at least one year prior to the date of the Invitation for Bid. Five percent (5%) will be added to the bid price quoted by each bidder or RFP respondent for a business that does not meet the definition of local business as set forth in MSD’s Procurement Regulations, Section 2A-14(a) when calculating price points for bid award.
An Excel Spreadsheet of the bid items is available for download. Click Here To Download
Plans/Bids Documents Available: March 3, 2010
Pre-Bid Meeting: Non-Mandatory Meeting -- March 12, 2010 at 1:30 P.M Location: Intersection of S. 4th Street and W. Oak Street . Bid Opening: March 19, 2010 at 12:00 P.M. Location: MSD Main Office Conference Room 1080 @ 700 W. Liberty St., Louisville, KY 40203
Proposed Project Completion Date: June 25, 2010
Questions: Eric G. Brady Louisville and Jefferson Co. Metropolitan Sewer District 700 W. Liberty St. Louisville, KY 40203 (502) 540-6616 E-mail: brady@msdlouky.org |
Addendums |
|
|
|